Posted on: January 9, 2023

WE Energy Cable Replacement Project on Pilgrim Rd

map 1

WE Energies is currently in the process of completing the final phase of an electric cable replacement project on Pilgrim Road.

This project consists of 21,688 linear feet of underground electric cables with various electric overhead installations located within easements and road right-of-way in the Village of Germantown. This project began on December 31, 2022 and will be completed by June 1, 2023. Please see the attached maps for your convenience.  Please understand that this is not a village project, but conducted by WE Energies and their subcontractors.