Donges Bay Road (Pilgrim Road to Magnolia Drive) - START DATE - June 20th
The work on Donges Bay Road includes full depth pulverization of the existing pavement, cutting out the soft spots in the sub-base, replacing and adding curb on the intersections, replacing sanitary sewer manhole chimneys, replacing broken water valve boxes, and placing new asphalt over the pulverized material.
Maple Road (Cedar Lane to Rockfield Road) - START DATE TBA
The work on Maple Road includes pulverizing the existing asphalt, cutting out the soft spots in the road base, and paving over with new asphalt.
Fieldstone Pass (Wagon Trail To Donges Bay Road) - COMPLETE
Country Aire Drive (Bonniwell Road to Pioneer Road) - STARTED AUGUST 6TH
The work on Country Aire Drive includes pulverizing the existing asphalt, cutting out the soft spots in the road base, placing some curb, storm and culvert work, and paving over with new asphalt.
Mequon Road Sidewalk (South East of Pilgrim Road) - COMPLETE